Roadway Paving
More details
Neighborhood Roadway RepairsThe City is actively working to improve neighborhood streets through an ongoing roadway…
The City is actively working to improve neighborhood streets through an ongoing roadway repair and repaving program. This effort focuses on restoring roadway segments in need of maintenance to improve safety, enhance driving conditions, and extend the lifespan of local infrastructure.
The schedule listed below reflects anticipated work timelines; however, all dates are approximate and subject to change due to weather conditions, material availability, or personnel scheduling. Updates will be made regularly to ensure the most accurate information is available, and residents are encouraged to check back often and plan accordingly for potential short-term impacts.
Approximately 2 weeks before construction operations begin, the City will be placing yard signs and/or door hangers at properties that adjoin the road repaving project to notify citizens. The yard signs will be re-used, please do not discard them.
What to Expect
During roadway repairs, residents and visitors may experience:
- Temporary lane closures
- Construction noise and heavy equipment activity
- Possible delays when entering or exiting neighborhoods
How You Can Prepare
To help minimize disruptions, we recommend:
- Allowing extra travel time when traveling through active work zones
- Following all posted detours, signage, and traffic control directions
- Keeping children and pets away from construction areas for their safety
Thank you for your patience and cooperation as we complete these important improvements to our neighborhood roadways.
You can email any questions you may have to paving@panamacity.gov, or call the Public Works Department at 850-691-4553.
Summer 2026 ScheduleRoadway · From · To · Entity · Start Date · Completion Date · StatusWest 9th St.
Roadway · From · To · Entity · Start Date · Completion Date · Status
West 9th St. · Hub Dr. · Mulberry Ave. · Housing · 05/15/2026 · 05/22/2026 · Completed
East 10th Ct. · Louisiana Ave. · MLK Blvd. · DNCRA · 06/01/2026 · 06/05/2026 · Completed
12th St. · Louisiana Ave. · MLK Blvd. · DNCRA · 06/10/2026 · 06/15/2026 · Completed
12th St. · Hamilton Ave. · Louisiana Ave. · DNCRA · 06/22/2026 · 06/24/2026 · Completed
East 16th St. · End · Wilson Ave. · DNCRA · 06/29/2026 · 08/03/2026 · Completed
Wilson Ave. · East 16th St. · Highway 98 · DNCRA · 07/06/2026 · 08/03/2026 · Completed
14th St. · MLK Blvd. · Mercedes Ave. · DNCRA/Housing · 08/05/2026 · 09/02/2026 · Completed
2nd St. · College Ave. · N. Center Ave. · Housing · 09/09/2026 · 09/18/2026 · Completed
Satsuma Ave. · East 6th St. · East 7th St. · MCRA · 10/12/2026 · 10/28/2026 · Completed
Williams Ave. · East 6th St. · East 8th St. · MCRA/Housing · 11/02/2026 · 12/11/2026 · In Progress
Bay Ave. · East 5th St. · East 8th St. · MCRA/Housing · 12/14/2026 · 01/08/2027 · On Schedule
4th St. · Maine Ave. · N. James Ave. · MCRA/Housing · 1/11/2027 · 03/05/2027 · On Schedule
Discovery Loop South to Hwy 390 + Frankford Avenue NorthDiscovery Loop South to Hwy 390Timeline: Paving expected to begin in Fall 2026.
Discovery Loop South to Hwy 390
- Timeline: Paving expected to begin in Fall 2026. The construction duration is approximately 8 weeks.
- Cost: Pavement design is being finalized, so the exact cost is being determined, approx. $900,000.
- Funding Source: SweetBay Development Agreement Funds within the Forest Park Mobility District.
- Project Details: Full removal and replacement of asphalt and the underlying base material.
- Paving Locations: from Hwy 390 to just south of Kestrel Street at the entrance to SweetBay
- Residential Impacts: One lane of traffic will be maintained during construction.
- Design done in-house by the Public Works Engineering division
Frankford Avenue North
- Timeline: Paving expected to begin in Fall 2026. The construction duration is approximately 8 weeks.
- Cost: Pavement design is being finalized, so the exact cost is being determined, approx. $900,000.
- Funding Source: SweetBay Development Agreement Funds within the Forest Park Mobility District.
- Project Details: Full removal and replacement of asphalt and the underlying base material.
- Paving Locations: from Robinson Bayou to Calhoun Avenue
- Residential Impacts: One lane of traffic will be maintained during construction.
- Design is a collaboration between Dewberry Engineers and the in-house Public Works Engineering division
State Avenue (23rd St. to Baldwin Ave.)Timeline: The goal is to have this section out to bid by the beginning of October.
- Timeline: The goal is to have this section out to bid by the beginning of October. The construction duration is approximately 12-14 weeks.
- Cost: Pavement design is being finalized, so the exact cost is being determined, approx. $2 million.
- Funding Source: Infrastructure Surtax
- Project Details: Remove the existing pavement and base material, lay geo-synthetic fabric over existing roadway sub-base materials to bridge organic soils that are present, install new base and asphalt material.
- Paving Locations: State Avenue from 23rd Street to Baldwin Ave.
- Residential Impacts: One lane of traffic will be maintained during construction.
- Design done in-house by the Public Works Engineering division. Planning to add a sidewalk along one side of the roadway in the future.
Florida Avenue (15th Street to 19th Street)Timeline: Project is in design.
- Timeline: Project is in design. The goal is to start this section at the end of 2026. The construction duration is approximately 8 weeks.
- Cost: Pavement design is being finalized, so the exact cost is being determined, approx. $450,000.
- Funding Source: Collaboration between the City and the new residential developers on the east and west sides of Florida Avenue.
- Project Details: Plans are being developed and will most likely involve milling and resurfacing at the northern and southern ends of Florida, closest to 15th and 19th Street, with the lower-lying middle portion of the road having additional base material added before repaving.
- Paving Locations: Florida Avenue between 15th and 19th Street
- Residential Impacts: One lane of traffic will be maintained during construction.
- Design done in-house by the Public Works Engineering division.
Venetian WayPaved toward the end of this year as part of the FEMA roads project.
Paved toward the end of this year as part of the FEMA roads project.