Major Facilities
More details
Martin Theatre, Tennessee House & The RitzThe Martin Theatre has been the heart of Downtown Panama City since its opening in…
The Martin Theatre has been the heart of Downtown Panama City since its opening in 1936, attracting visitors and residents alike. This Art Deco theatre has been home to movie showings, musicals, plays, dance productions and concerts until storm damage closed the building in 2018. Owned by the Panama City Downtown Improvement Board (DIB) since 1987, the City of Panama City is working to rebuild and restore this iconic landmark.
The Panama City Commission began accepting bids for construction in January 2024 and awarded the bid to Burke Construction Group in June 2024. Shortly after, the City hosted a Groundbreaking Ceremony and Block Party on September 13, 2024. The rebuild will pay tribute to the theatre’s history while updating the space with modern technologies and standards.
The Martin Theatre rebuild is projected to be completed by late fall to winter 2027. The main theatre space is being updated with 488 new seats, ADA accessibility, a new dressing room, an expanded orchestra pit and the installation of advanced lighting and sound systems.
The theatre is expanding on either side of the original blueprint to include the Ritz and the Tennessee House. What was once the former DIB building will become The Ritz, paying tribute to the Martin Theatre’s original name. The Ritz will house a lobby, concessions and a 1920s-style speakeasy lounge. On the other side of the theatre is the Tennessee House, which will replace the original green room. It will also feature reception and dining areas, with a balcony overlooking Four Points Plaza.
As the project nears completion, the City is seeking a new operator for the Martin Theatre, as the original operator, Martin Theatre Inc., permanently closed in September 2025. This closure did not affect the construction of the physical building, and the City is looking to award a theatre management contract once the Martin Theatre opens.
The restoration of the Martin Theatre is part of a broader effort to revitalize Downtown Panama City, while preserving the City’s classic history.
- Location: 409 Harrison Ave.
- Estimated Start Date: September 13, 2024 (groundbreaking)
- Estimated Completion Date: Late fall to winter 2027
- Funding Source: The rebuilding project is almost fully funded by FEMA, which is providing ~$31,000,000, with ~$2,200,000 from the City.
- Estimated Cost: ~$33,200,000
Latest Update - October 2026: A Request for Proposals (RFP) for the operation of the theatre has closed as of October 14, 2026. The City is reviewing the RFP.
- Martin Theatre: The auditorium is taking shape with concrete being poured for the new seating area. In the lobby, crews are advancing plumbing, electrical, ceiling, and framing work, while HVAC improvements continue in the basement.
- The Tennessee House: Work continues on the building's exterior with insulation, storefront installation, and preparations for future finishes. Crews will also install the rooftop HVAC chiller while continuing ductwork and electrical work inside.
- The Ritz: Exterior improvements continue with new storefront systems and impact-resistant glass. Inside, crews are installing ceilings and insulation, while rooftop HVAC connections and elevator deliveries move the project closer to completion.
Panama City MarinaAs did many structures in Panama City, the Downtown Marina sustained significant…
As did many structures in Panama City, the Downtown Marina sustained significant hurricane damage and is currently undergoing reconstruction efforts. While the marina’s boat ramp currently serves as a launch point for boats and a hub for fishing, the City is working to expand the Downtown Marina’s functionality to support Panama City’s coastal recreation.
- Location: 1 Harrison Ave.
- Estimated Start Date: Summer 2026 (first 50 slips)
- Estimated Completion Date: Spring 2027
- Funding Source: FEMA + 150M Recovery Loan or P3 Partnership - TBD
- Estimated Cost: $10,000,000
Background: As the City began drafting marina improvement plans, the City Commission voted to use $5 million of FEMA funding to rebuild marina infrastructure. In December 2024, the Commission approved a $149,750 partnership with Panhandle Engineering to enhance the existing boat ramp by reducing its steepness in response to citizen feedback.
Rebuilding efforts resulted in the City reopening the marina’s fuel dock in March 2025, allowing boaters to purchase fuel, bait, and other amenities. After four months of operation, the decision was made to permanently close the Downtown Marina fuel dock due to consistent operational losses that did not cover basic expenses.
As 2025 came to an end, the City Commission voted to install the first 50 boat slips without a private partnership, but plans to bid the slips out. Slip construction cost is expected to be approximately $10 million to build Phase 1 with a total of 50 wet slips: 20 540-foot slips, 16 60-foot slips and 14 70-foot slips.
The City is continuing progress on planning and rebuilding the Downtown Marina while expanding public engagement opportunities. Following the December 16 City Commission meeting, staff began developing a two-phase proposal that includes a scaled-down “bootstrap” option to advance near-term construction and a comprehensive long-term plan addressing design, infrastructure, and utilities. In January, the City hosted a series of Downtown Marina charrettes at City Hall, where more than 200 residents, stakeholders, and planners participated in discussions about waterfront access, resilience, public spaces, and economic vitality.
On April 1-2, 2026, Dover, Kohl & Partners presented the next phase of planning for the future of the Panama City Marina and downtown waterfront. The team shared updated design ideas, summaries of community feedback, and new visual renderings based on input from residents and other interested parties. Moving forward, the planning team will review all input and use it to help refine the final plans for the marina and waterfront area.
April 2026 Marina Presentation & Concepts
Latest Update - October 2026: The Downtown Marina boat ramp has reopened following storm damage from Hurricane Isaias. The City is moving forward with a revised plan to rebid the marina construction in phases, beginning with the east basin docks and breakwater, followed by additional dock construction. The updated approach is intended to encourage competitive bids and help control costs by separating specialized marine construction work. The City also accepted a proposal from St. Joe Development Company to provide alternative financing for the first 50 boat slips, contingent on reaching a marina management agreement. The boat ramp will be completed as a separate phase, with partial grant funding. The City is preparing revised bid documents and plans to seek proposals from qualified marine contractors.
St. Andrews MarinaThe St. Andrews Marina, built in 1960, is undergoing a full restoration that began in…
The St. Andrews Marina, built in 1960, is undergoing a full restoration that began in October 2024. Before groundwork began, the City Commission voted to enter a 30-year ground lease agreement with St. Andrews Marina Partners, LLC to increase the existing marina size by 50%. Moving forward with public-private partnerships, Moffat & Nickols is providing architecture and engineering services.
The rebuild, overseen by Gorman Marine, is being completed in multiple phases that have introduced 160 new boat slips, bulkhead wall reconstruction, repairs to the Bayview Avenue boardwalk, fuel dock repairs, and repairs to the ship store. The restoration also includes replacing the original concrete floating docks with wooden piers and pilings to facilitate easier future repairs.
- Location: 3151 W 10th St.
- Estimated Start Date: October 22, 2024
- Estimated Completion Date: Summer 2026
- Funding Source: City of Panama City & SAMP, LLC
- Estimated Cost: ~$25 million
Latest Update - October 2026: St. Andrews Marina continues to see strong use, with most boat slips currently under lease. During Hurricane Isaias, the marina basin provided shelter for numerous vessels seeking protection from the storm.
Bulkhead repairs are moving forward, with purchase orders issued and material submittals currently under review.
Mlk Jr. Recreation CenterSince its opening in 1982, the MLK Jr.
Since its opening in 1982, the MLK Jr. Recreation Center has served as a community pillar for residents of all ages. After 26 years of community use, the Rec. Center closed in 2018 after enduring irreversible damage from Hurricane Michael. As the City began moving forward to rebuild the Rec. Center, the City Commission approved a new design by CCR Architects and Interiors and demolished the original building in 2022, taking the first major step toward reconstructing the MLK Jr. Recreation Center. Shortly after, the City held a groundbreaking ceremony on the original Rec. Center grounds in February 2024, followed by the issuance of a building permit in April 2024.
As construction began, Javien Elliot, a Panama City Native, was hired as the MLK Jr. Recreation Center Manager in August 2025. A graduate of Rutherford High School, Elliot grew up going to the Rec. Center before he went on to play football at FSU and in the NFL. Elliot’s hire was followed by the adoption of eight full-time and 11 part-time team members to staff the center.
After 22 months of construction by Burke Construction Group (fact-check this), the newly rebuilt MLK Jr. Recreation Center held a soft opening on December 15, 2025. The facility includes an open-play gym, fitness room, indoor basketball courts, culinary kitchen, arts and crafts studio, reading room, community meeting spaces, sound engineering and recording studio, e-sports room, STEM lab, outdoor playground, outdoor basketball courts and multipurpose outdoor fields. The site also includes an $80,000 sculpture, “Legacy in Motion,” created by local artist George Gadson. This marks Panama City’s largest public art investment and represents the City’s past, present, and future.
Following the soft opening, the City Commission voted to enact a paid membership structure, effective March 1, 2026.
- Location: 705 E 14th Ct.
- Estimated Start Date: February 16, 2024
- Estimated Completion Date: January 16, 2026
- Funding Source: FEMA & City
- Estimated Cost: $21 million total ($15 million from FEMA, $6 million from the City)